Today, on the14th of October 2015, at the Commercial Court in Zagreb, with more than 2/3 of the votes The Pre-Bankruptcy Settlement of Adriadiesel d.d. has been concluded.

With this settlement Adriadiesel, as a manufacturer of diesel generators and power plants, continues with the positive business trend and with entering new markets. The continuous

development of new technologies, continuous education and innovations are the strategic backbone of the current and future business of Adriadiesel.

Thank you all.

Rate this item
(0 votes)

Bureau Veritas as one of the world's leading accredited certification society for the monitoring, classification and certification has confirmed our commitment

to the development, production, testing and servicing of diesel engines and other power equipment according to Bureau Veritas NR320 requirements relating

to compliance with the procedures of the quality system.

Rate this item
(0 votes)

Generator sets testing for two constructions is currently in the final stage in the production facility of Adriadiesel.

Construction 722 with  auxiliary engines MAN 3x7L23 / 30HMK2, produced in ADRIADIESEL, is for the shipyard Uljanik d.d. Testing and handover of the generator sets are planned for

the beginning of January 2016. The event will be attended by representatives of the owner and shipyard. The same generator sets are also contracted for the new construction 723, for the shipyard Uljanik d.d. as well and the delivery of the same is planned for the end of June 2016.

Construction 326 with  auxiliary enginesMAN 3x7L23 / 30HMK2, also produced in ADRIADIESEL, is for the shipyard Brodotrogir d.d. Final assembly and the planned handover of this generator set is planned for the end of January 2016.

Generator sets testing for two constructions is currently in the final stage in the production

facility of Adriadiesel.

Construction 722 with  auxiliary engines MAN 3x7L23 / 30HMK2, produced in ADRIADIESEL,

is for the shipyard Uljanik d.d. Testing and handover of the generator sets are planned for

the beginning of January 2016. The event will be attended by representatives of the owner 
and shipyard. The same generator sets are also contracted for the new construction 723,

for the shipyard Uljanik d.d. as well and the delivery of the same is planned for the end of June 2016.

Construction 326 with  auxiliary enginesMAN 3x7L23 / 30HMK2, also produced in ADRIADIESEL,

is for the shipyard Brodotrogir d.d. Final assembly and the planned handover of this generator

set is planned for the end of January 2016.