Sunday, 10 July 2016 13:23

The final stage of testing generatorsets constructions 722 and 326

Rate this item
(0 votes)

Generator sets testing for two constructions is currently in the final stage in the production facility of Adriadiesel.

Construction 722 with  auxiliary engines MAN 3x7L23 / 30HMK2, produced in ADRIADIESEL, is for the shipyard Uljanik d.d. Testing and handover of the generator sets are planned for

the beginning of January 2016. The event will be attended by representatives of the owner and shipyard. The same generator sets are also contracted for the new construction 723, for the shipyard Uljanik d.d. as well and the delivery of the same is planned for the end of June 2016.

Construction 326 with  auxiliary enginesMAN 3x7L23 / 30HMK2, also produced in ADRIADIESEL, is for the shipyard Brodotrogir d.d. Final assembly and the planned handover of this generator set is planned for the end of January 2016.

Generator sets testing for two constructions is currently in the final stage in the production

facility of Adriadiesel.

Construction 722 with  auxiliary engines MAN 3x7L23 / 30HMK2, produced in ADRIADIESEL,

is for the shipyard Uljanik d.d. Testing and handover of the generator sets are planned for

the beginning of January 2016. The event will be attended by representatives of the owner 
and shipyard. The same generator sets are also contracted for the new construction 723,

for the shipyard Uljanik d.d. as well and the delivery of the same is planned for the end of June 2016.

Construction 326 with  auxiliary enginesMAN 3x7L23 / 30HMK2, also produced in ADRIADIESEL,

is for the shipyard Brodotrogir d.d. Final assembly and the planned handover of this generator

set is planned for the end of January 2016.

Read 3271 times Last modified on Sunday, 10 July 2016 13:39